When upgrading systems with b+ Add-Ons installed (TESII, TESICNC, TEFC, BPCORE…) during the SUM phase some issues may arise.
Add-On Selection
Current phase: PREP_EXTENSION/IS_SELECT
...
The ACPs availables are:
ACP for para TEFC → ACP_TEFC_S4.SAR (Available in b+ SII section in the client portal)
ACP for para TESII → ACP_TESII_S4_02.SAR (Available in b+ ElectronicInvoice in the client portal)S4CORE103.SAR
These ACPs can be downloaded from the following link:
If this process does not work, please to contact to the product support through the email: es-bplussiteadmin@techedgegroup.com.
You will have to indicate the release and SP level of the next components for the target system:
...
Product team will create the proper ACP files needed so you can load them and continue with the upgrade.
CRT Conflict - TESII/TESICNC
Current phase: PREP_EXTENSION/CONFLICT_CHECK
The SUM will stop here and will show messages like these ones:
...
In this case you need to download transport request OSDK902777 (ConflictResolution.zip) from the portal and install it in the system . After that restart the SUM phase and check those errors do not appear again.
View file | ||
---|---|---|
|
If you have any problem or questions you can contact to us through the email: es-bplussiteadmin@techedgegroup.com
It is recommended that you send us the CONFLCHK.LOG and SPDA_CONFLCHK.LOG files by e-mail.